The interior walls are complete and windows and doors are going in. Joe is going to try to complete out the electrical so we can get the inspection complete in order to start placing the insulation. The roof plywood is half way done and Joseph will be completing the second half hopefully by the end of the day since it is going to start raining again later today and all day tomorrow. The ultimate Friday night goal is to have the place "dryed in". Jo-Fish has volunteered to stay a another whole week and work with our caretaker, Robert to finish out more work. We are going to contract out the drywall and roof shingles since we did not get to that phase of the project due to all the weather and unforeseen issues that had to be overcome along the way.